The Lyra Programme: Check list
This check list is intended to help you plan an orderly and timely course through the Lyra Programme. It summarises what you need to do and when you need to do it.
The deadlines in the check list are the latest dates for any library to carry out the relevant action. Many libraries will have schedules with substantially earlier deadlines for all of these actions.
If you have any questions or problems with any of the actions in this check list, please talk to your Account Manager or email sales@talis.com.
Talis Alto and Talis Prism start
| Milestone & Actions |
Deadline |
Note |
| Install Talis Alto |
Now |
At least some staff should already be using a version of Talis Alto. |
| Install Talis Alto |
Now |
Talis Prism should be the OPAC in at least some parts of your library service. |
Lyra Programme start
| Milestone & Actions |
Deadline |
Note |
| Order the Lyra Foundation package |
Now |
A prerequisite for subsequent actions. |
| Schedule Lyra training for cataloguing staff |
Now |
To ensure you get the training when you need it. |
System preparation
| Milestone & Actions |
Deadline |
Note |
| Server Health Check passed |
End May 06, recommended |
Must be scheduled with Talis. Get to passed status by this date. |
| - Upgrade hardware if recommended |
|
Order as early as possible. |
| - Schedule database expansion if required |
|
Work to be done by Talis Client Services. |
| Desktop Operating System up to spec |
End May 06, recommended |
Minimum requirement: Windows 2000, Windows XP recommended. |
Conversion analysis
| Milestone & Actions |
Deadline |
Note |
| Run the marc_analysis script |
Summer 06, recommended |
Refer to the MARC Conversion Guide for details of actions in this section. |
| Act on the report |
Summer 06, recommended |
|
| - Schedule database expansion if required |
Summer 06, recommended |
To convert data not covered in the standard mappings. |
Lyra Foundation phase (Talis Alto and Talis Prism everywhere)
| Milestone & Actions |
Deadline |
Note |
| Talis Alto in use for all acquisitions and cataloguing, and linked to Talis Base 2.0 |
30 Sep 2006 |
Talis Base 1.0 will be withdrawn on this date. Staff still using Talis Text will not be able to source bibliographic records for orders or new stock. |
| Talis Alto in use by all staff for all functions; Talis Text decommissioned |
End Oct 06, recommended |
Prerequisite to Talis Alto 3.0 by December 2006. Talis Text is not supported once the Alto 3.0 upgrade has taken place. Delaying this will condense your timescale for making the move to Talis Alto 3.0 by the end of the year. |
| Apply the Talis Alto automatic upgrade facility to all PCs and cease use of the manual PC-by-PC install. |
End Oct 06, recommended |
The automatic upgrade makes it quicker, cheaper and easier to rollout new versions of Talis Alto. If you have not implemented it, you may struggle to rollout the required sequence of upgrades in a timely way. |
| Upgrade to Talis Alto 2.1. |
End Oct 06, recommended |
Prerequisite to Talis Alto 3.0. Make sure you have time to get to 3.0 by the end of the year at the absolute latest. |
| Talis Prism in use exclusively as your OPAC; TalisWeb decommissioned |
End Oct 06, recommended; before Talis Alto 3.0 upgrade |
Prerequisite to Talis Alto 3.0. TalisWeb is not supported once the Alto 3.0 upgrade has taken place. |
| Upgrade to Talis Prism 2.0 |
Optional |
It is possible to upgrade to Talis Prism 2.0 before or after Talis Alto 3.0. It is also possible to go straight to Talis Prism 2.1. But, without Talis Prism 2.0 it will not be possible to review the display of MARC 21 records from conversion test runs. |
| Upgrade to Talis Alto 3.0 |
31 Dec 2006, absolute latest |
Essential for ISBN-13 compliance by this date. Without it, your library’s ability to procure, catalogue and circulate new stock will be impaired: any new title with a 13 digit ISBN will not be processed. Also the pre-requisite for bibliographic conversion preparation and testing. |
Bibliographic record conversion
| Milestone & Actions |
Deadline |
Note |
| Download and install MARC Conversion Manager 1.0 |
After Talis Alto 3.0 upgrade |
Contact sales@talis.com for details. |
| Practice and do MARC 21 cataloguing |
After Talis Alto 3.0 upgrade |
|
| Identify records for checking in conversion |
|
This can be started now. |
| Practice converting bibliographic records |
|
Run the MARC Conversion Manager on selected records, and check the results. Consult Talis about any issues or further requirements. |
| Convert all bibliographic records and sign-off this stage |
Before upgrading to Talis Alto 4.0. |
Let Talis know that you have completed your bibliographic conversion. It will not be possible to upgrade to Alto 4.0 or higher until the bibliographic conversion has been carried out. |
Lyra completion
| Milestone & Actions |
Deadline |
Note |
| Upgrade to Talis Alto 4.0 |
Soon after bibliographic covnersion, recommended |
Prerequisite to building new indexes from your MARC 21 bibliographic records and converting your authority records. |
| Install new indexing tools & build new indexes from your MARC 21 bibliographic records |
Together with Talis Alto 4.0 upgrade |
|
| Convert all authority records and sign-off this stage |
Soon after Talis Alto 4.0 upgrade |
The process includes authorising your bibliographic record headings and reporting. A prerequisite to using the new MARC 21 authority control features in Talis Alto 4.0, if you already have authority records. |
| Upgrade to Talis Prism 2.1 |
Soon after authority record conversion |
To have a catalogue that uses the new search system and indexes, with real time updates, and that reflects current authorities for cross-referencing. |